I have a question.
Assuming the below performance report:
Day 1
Actual 1
Target 1
Achieve 100%
Day 2
Actual 1
Target 1
Achieve 100%
Day 3
Actual 9
Target 10
Achieve 90%
Which method do you use to report the Achievement for the 3 days?
1. Do you take the average of 100%,100%,90% to give 97%
OR
2. Do you sum Actual (Day1+Day2+Day3 = 11) / Target (Day1+Day2+Day3 =12) to give 92%
:think:
Assuming the below performance report:
Day 1
Actual 1
Target 1
Achieve 100%
Day 2
Actual 1
Target 1
Achieve 100%
Day 3
Actual 9
Target 10
Achieve 90%
Which method do you use to report the Achievement for the 3 days?
1. Do you take the average of 100%,100%,90% to give 97%
OR
2. Do you sum Actual (Day1+Day2+Day3 = 11) / Target (Day1+Day2+Day3 =12) to give 92%
:think:
Last edited: